Stainless Project Chimney System Installation

1.1 preparation of construction plan
1.2 carefully organize relevant personnel are familiar with and understand the chimney fabrication and installation drawings, construction specifications and technical requirements of the construction program, to lay the foundation for the chimney construction.
1.3 technical staff carefully detailed technical tests to relevant personnel, and make technical disclosure records to ensure workers are able to grasp the essentials related to various types of operations.
2, construction conditions to prepare:
2.1 electricity; provide 50 kilowatts, 380-volt power supply to the construction site computer control room.
2.2 leveling vacant site construction, ease of mechanical equipment furnished and have enough space to store the material on-site.
2.3 ensure that the site needed to enter the construction site crane roads open.
2.4 Fire equipment according to requirements stored at the job site.
2.5 site with water according to the construction site layout plan laying water pipes, to ensure the construction of adequate clean water.
2.6 prepare adequate nighttime construction lighting and secure.
2.7 tower scaffolding set up meet the safety requirements (for hand lay-up FRP chimney butt).

Back】 
Stainless Flue system : Stainless steel chimney system / Stove pipe/ Fireplace chimney/ Heater flue kits / twin wall insulated chimney / Wood stove chimney system / Carbon chimney system / Chimney parts / Environmental protection equipment / Dust clean equipment / Hotel venting system / Ventilation projects /
Stainless steel sheet metal : Hotel dirty clothes well / Hotel corrupt garment slot / Stainless Lampblack tube / High Temperature Venting pipes / HVAC equipment system / Industry Steel chimney system / Mutual Inductor screening shell / GIS shell / Air duct / Air pipe / Wind flue / Wind pipe /
Precision Machining : Polishing / Brushed Metal / Handmade Argon Arc Welding / CNC machine/ laser cutting / Metal products design /

Copyringht © 2013 Suzhou Ruilun Metal Products Co., Ltd. www.ruilunmetal.com Name:Eric Gao Tel:13812610917 E-mail:eric@metalflue.com